Decision queue
Ranked actions for the week, ordered by cost impact and urgency. The week is published. Confirm the supplier follow-up and floor release details against the package.
34
Open decisions
34 actions awaiting review
$268,125
Total risk
aggregate downtime cost if unresolved
8
Machines loaded
655 hrs across the week
8
Supplier actions
8 materials pending review
Planning path
The weekly operating path is complete.
>
Planning path
The weekly operating path is complete.
Order 27,118 lb KI20 from APEX
$70,780 at risk7 scheduled runs on M04, M05, M07, M11 depend on this material. $70,780/day downtime risk if delayed.
Order 17,844 lb KI34 from APEX
$24,437.5 at risk3 scheduled runs on M08, M17, M18 depend on this material. $24,437.5/day downtime risk if delayed.
Order 13,055 lb 4641 from CENTEX
$16,105 at risk2 scheduled runs on M17, M18 depend on this material. $16,105/day downtime risk if delayed.
Order 10,969 lb U2091 from APEX
$12,295 at risk2 scheduled runs on M19 depend on this material. $12,295/day downtime risk if delayed.
M05 lot 228 SDH has minimal buffer
$9,760 at riskCompletes 2026-02-15 for due date 2026-02-15, leaving 0 day buffer. Consider adding buffer time.
M04 lot 106 has minimal buffer
$9,740 at riskCompletes 2026-02-14 for due date 2026-02-14, leaving 0 day buffer. Consider adding buffer time.
Order 4,247 lb 4271 from CENTEX
$9,610 at risk1 scheduled runs on M08 depend on this material. $9,610/day downtime risk if delayed.
M05 lot 228 SDH has minimal buffer
$8,460 at riskCompletes 2026-02-24 for due date 2026-02-25, leaving 1 day buffer. Consider adding buffer time.
M07 lot 398 has minimal buffer
$7,315 at riskCompletes 2026-02-16 for due date 2026-02-17, leaving 1 day buffer. Consider adding buffer time.
M08 lot 833 has minimal buffer
$7,210 at riskCompletes 2026-02-15 for due date 2026-02-16, leaving 1 day buffer. Consider adding buffer time.
M08 lot 504 has minimal buffer
$6,772.5 at riskCompletes 2026-02-18 for due date 2026-02-19, leaving 1 day buffer. Consider adding buffer time.
Order 6,286 lb U9154 from APEX
$6,590 at risk1 scheduled runs on M19 depend on this material. $6,590/day downtime risk if delayed.
M11 lot 638 has minimal buffer
$6,562.5 at riskCompletes 2026-02-16 for due date 2026-02-17, leaving 1 day buffer. Consider adding buffer time.
M18 lot 575 SD has minimal buffer
$6,555 at riskCompletes 2026-02-18 for due date 2026-02-19, leaving 1 day buffer. Consider adding buffer time.
Order 5,692 lb U5182 from APEX
$6,410 at risk1 scheduled runs on M17 depend on this material. $6,410/day downtime risk if delayed.
Order 3,448 lb 4016 from STERLING
$6,290 at risk1 scheduled runs on M18 depend on this material. $6,290/day downtime risk if delayed.
M17 lot 501 has minimal buffer
$6,195 at riskCompletes 2026-02-17 for due date 2026-02-18, leaving 1 day buffer. Consider adding buffer time.
M17 lot 575 SD has minimal buffer
$5,550 at riskCompletes 2026-02-23 for due date 2026-02-24, leaving 1 day buffer. Consider adding buffer time.
M04 lot 106 has minimal buffer
$5,520 at riskCompletes 2026-02-20 for due date 2026-02-21, leaving 1 day buffer. Consider adding buffer time.
M18 lot 501 has minimal buffer
$5,070 at riskCompletes 2026-02-22 for due date 2026-02-23, leaving 1 day buffer. Consider adding buffer time.
M07 lot 398 has minimal buffer
$5,022.5 at riskCompletes 2026-02-25 for due date 2026-02-26, leaving 1 day buffer. Consider adding buffer time.
M19 lot 587 has minimal buffer
$4,590 at riskCompletes 2026-02-19 for due date 2026-02-20, leaving 1 day buffer. Consider adding buffer time.
M17 lot 876 has minimal buffer
$4,410 at riskCompletes 2026-02-20 for due date 2026-02-21, leaving 1 day buffer. Consider adding buffer time.
M18 lot 197 has minimal buffer
$4,290 at riskCompletes 2026-02-21 for due date 2026-02-22, leaving 1 day buffer. Consider adding buffer time.
M19 lot 840 has minimal buffer
$4,185 at riskCompletes 2026-02-26 for due date 2026-02-27, leaving 1 day buffer. Consider adding buffer time.
M19 lot 840 has minimal buffer
$4,110 at riskCompletes 2026-02-19 for due date 2026-02-20, leaving 1 day buffer. Consider adding buffer time.
M19 overbooked — 200% peak utilization
$3,600 at risk85.9 machine hours across the week. 1 overloaded days, 1 tight days.
M18 overbooked — 119% peak utilization
$690 at risk106.1 machine hours across the week. 1 overloaded days, 2 tight days.
M04 at 100% utilization — no buffer for changeover
$0 at risk76.3 machine hours across the week. 0 overloaded days, 3 tight days.
M05 at 100% utilization — no buffer for changeover
$0 at risk91.1 machine hours across the week. 0 overloaded days, 3 tight days.
M08 at 100% utilization — no buffer for changeover
$0 at risk79.9 machine hours across the week. 0 overloaded days, 2 tight days.
M07 at 100% utilization — no buffer for changeover
$0 at risk70.5 machine hours across the week. 0 overloaded days, 2 tight days.
M11 at 100% utilization — no buffer for changeover
$0 at risk37.5 machine hours across the week. 0 overloaded days, 1 tight days.
M17 at 100% utilization — no buffer for changeover
$0 at risk107.7 machine hours across the week. 0 overloaded days, 3 tight days.
Completed
3 resolved items this week — no action needed.
>
Completed
3 resolved items this week — no action needed.
All demand is scheduled — load plan is complete
18 slots covering 18 requirement lines, all placed on the board.
Faraday workbook variant needs an explicit source-of-truth decision — resolved
Two Faraday variants exist; the newer `Q1` workbook is the safer default, but the choice should be explicit in the product.
Publish package generated — ready for handoff
Week of 2026-02-09 published scenario publish package