Supplier actions
What to order, from whom, by when. Each action links to the machine slots it protects. The week is published. Confirm the supplier follow-up and floor release details against the package.
8
Supplier reviews
$152,517.5/day combined risk
18
Blocked slots
machine commitments carrying material risk
9
Materials tracked
1 covered, 8 need action
Planning path
The weekly operating path is complete.
>
Planning path
The weekly operating path is complete.
Action queue
8 supplier actions · $152,517.5/day combined risk
Review and confirm each order. Every action links to the machine slots it protects.
KI20
APEXOrder 27,118 lb · needed by Thu, Feb 12
Protects
M04 lot 106 (2026-02-12 – 2026-02-14)
M05 lot 228 SDH (2026-02-13 – 2026-02-15)
M07 lot 398 (2026-02-15 – 2026-02-16)
M11 lot 638 (2026-02-15 – 2026-02-16)
M04 lot 106 (2026-02-19 – 2026-02-20)
M05 lot 228 SDH (2026-02-23 – 2026-02-24)
M07 lot 398 (2026-02-24 – 2026-02-25)
Risk
$70,780
$52,380 downtime + $18,400 restart
On hand
4,200 lb
Open PO: 1,400 lb
Coverage
1.2 days
without this order
Order qty
27,118 lb
31,518 lb total demand
KI34
APEXOrder 17,844 lb · needed by Mon, Feb 16
Protects
M17 lot 501 (2026-02-16 – 2026-02-17)
M08 lot 504 (2026-02-17 – 2026-02-18)
M18 lot 501 (2026-02-21 – 2026-02-22)
Risk
$24,437.5
$18,037.5 downtime + $6,400 restart
On hand
3,800 lb
Open PO: 2,200 lb
Coverage
1.4 days
without this order
Order qty
17,844 lb
22,644 lb total demand
4641
CENTEXOrder 13,055 lb · needed by Tue, Feb 17
Protects
M18 lot 575 SD (2026-02-17 – 2026-02-18)
M17 lot 575 SD (2026-02-22 – 2026-02-23)
Risk
$16,105
$12,105 downtime + $4,000 restart
On hand
2,800 lb
Open PO: 1,000 lb
Coverage
0.8 days
without this order
Order qty
13,055 lb
15,655 lb total demand
U2091
APEXOrder 10,969 lb · needed by Wed, Feb 18
Protects
M19 lot 840 (2026-02-18 – 2026-02-19)
M19 lot 840 (2026-02-25 – 2026-02-26)
Risk
$12,295
$8,295 downtime + $4,000 restart
On hand
2,100 lb
Open PO: 800 lb
Coverage
0.5 days
without this order
Order qty
10,969 lb
12,669 lb total demand
4271
CENTEXOrder 4,247 lb · needed by Sat, Feb 14
Protects
M08 lot 833 (2026-02-14 – 2026-02-15)
Risk
$9,610
$7,210 downtime + $2,400 restart
On hand
1,200 lb
Open PO: 500 lb
Coverage
0.6 days
without this order
Order qty
4,247 lb
4,747 lb total demand
U9154
APEXOrder 6,286 lb · needed by Wed, Feb 18
Protects
M19 lot 587 (2026-02-18 – 2026-02-19)
Risk
$6,590
$4,590 downtime + $2,000 restart
On hand
900 lb
Open PO: 400 lb
Coverage
0.3 days
without this order
Order qty
6,286 lb
6,386 lb total demand
U5182
APEXOrder 5,692 lb · needed by Thu, Feb 19
Protects
M17 lot 876 (2026-02-19 – 2026-02-20)
Risk
$6,410
$4,410 downtime + $2,000 restart
On hand
1,500 lb
Open PO: 600 lb
Coverage
0.4 days
without this order
Order qty
5,692 lb
6,592 lb total demand
4016
STERLINGOrder 3,448 lb · needed by Fri, Feb 20
Protects
M18 lot 197 (2026-02-20 – 2026-02-21)
Risk
$6,290
$4,290 downtime + $2,000 restart
On hand
3,500 lb
Open PO: 1,800 lb
Coverage
0.9 days
without this order
Order qty
3,448 lb
7,548 lb total demand
Coverage summary
Raw material coverage
All tracked materials with on-hand inventory, open POs, demand, gap, and coverage in days.
| Raw Material | On Hand | Open PO | Demand | Gap | Coverage |
|---|---|---|---|---|---|
U9154 | 900 | 400 | 6,200 | 4,900 | 0.3 days |
U5182 | 1,500 | 600 | 6,400 | 4,300 | 0.4 days |
U2091 | 2,100 | 800 | 12,300 | 9,400 | 0.5 days |
4271 | 1,200 | 500 | 4,700 | 3,000 | 0.6 days |
4641 | 2,800 | 1,000 | 15,500 | 11,700 | 0.8 days |
4016 | 3,500 | 1,800 | 7,400 | 2,100 | 0.9 days |
KI20 | 4,200 | 1,400 | 30,900 | 25,300 | 1.2 days |
KI34 | 3,800 | 2,200 | 22,200 | 16,200 | 1.4 days |
FP71045R✓ | 1,500 | 200 | 0 | — | 999.0 days |